| Radiance Assisted Living | ||||||
| Soft Costs | ||||||
| ARCHITECTURAL FEES - 1.5% | ||||||
| feasibility study | 2,000 | 90,000 | ||||
| construction documents | 17,000 | 765,000 | ||||
| construction supervision & arch details | 50,000 | 2,250,000 | ||||
| ENGINEERING FEES | - | |||||
| structural engineering - 1% | 46,440 | 2,089,800 | ||||
| mechanical engineering - 0.3% | 13,932 | 626,940 | ||||
| electrical engineering - 0.3% | 13,932 | 626,940 | ||||
| energy & acoustical evaluation - 0.3% | 13,932 | 626,940 | ||||
| PERMITS: | - | |||||
| Use permit | 1,000 | 45,000 | ||||
| MUP sign | 1,000 | 45,000 | ||||
| Building permit | 1,000 | 45,000 | ||||
| LEGAL fees: | - | |||||
| Purchase & ownership documents | 3,000 | 135,000 | ||||
| ACCOUNTING fees | 1,000 | 45,000 | ||||
| BUYOUT leases | 1,500 | 67,500 | ||||
| PLAN & FEASIBILITY STUDY | - | |||||
| writing prospectus and plan | 5,000 | 225,000 | ||||
| advertising & marketing | 50,000 | 2,250,000 | ||||
| COST ESTIMATOR | 1,000 | 45,000 | ||||
| OFFICE EXPENSES | 10,000 | 450,000 | ||||
| PROJECT MANAGEMENT | - | |||||
| construction & project manager - 1.5% | 70,000 | 3,150,000 | ||||
| CLOSING COSTS | 10,000 | 450,000 | ||||
| CASH NEEDED TO CARRY UNSOLD UNITS | 40,000 | 1,800,000 | ||||
| ACCRUED INTEREST ON LOANS | 200,000 | 9,000,000 | ||||
| LOAN FEE | 4,000 | 180,000 | ||||
| INSURANCE | 10,000 | 450,000 | ||||
| TAXES | 20,000 | 900,000 | ||||
| DEVELOPER OR INVESTOR FEES | 15,000 | 675,000 | ||||
| RESERVE FUND FOR FUTURE | 50,000 | 2,250,000 | ||||
| - | ||||||
| 650,736 | 29,283,120 | |||||
| say | 700,000 | 31,500,000 | ||||