Radiance Assisted Living
Soft Costs
ARCHITECTURAL FEES - 1.5%
     feasibility study         2,000            90,000
     construction documents       17,000          765,000
     construction supervision & arch details       50,000       2,250,000
ENGINEERING FEES                    -  
     structural engineering - 1%       46,440       2,089,800
     mechanical engineering - 0.3%       13,932          626,940
     electrical engineering - 0.3%       13,932          626,940
     energy & acoustical evaluation - 0.3%       13,932          626,940
PERMITS:                    -  
      Use permit         1,000            45,000
      MUP sign         1,000            45,000
     Building permit         1,000            45,000
LEGAL  fees:                    -  
      Purchase & ownership documents         3,000          135,000
ACCOUNTING fees         1,000            45,000
BUYOUT leases         1,500            67,500
PLAN & FEASIBILITY STUDY                    -  
    writing prospectus and plan         5,000          225,000
    advertising & marketing       50,000       2,250,000
COST ESTIMATOR         1,000            45,000
OFFICE EXPENSES       10,000          450,000
PROJECT MANAGEMENT                    -  
     construction & project manager - 1.5%       70,000       3,150,000
CLOSING COSTS       10,000          450,000
CASH NEEDED TO CARRY UNSOLD UNITS       40,000       1,800,000
ACCRUED INTEREST ON LOANS     200,000       9,000,000
LOAN FEE         4,000          180,000
INSURANCE       10,000          450,000
TAXES       20,000          900,000
DEVELOPER OR INVESTOR FEES       15,000          675,000
RESERVE FUND FOR FUTURE       50,000       2,250,000
                   -  
    650,736     29,283,120
say     700,000     31,500,000